350 East Cermak, Chicago, IL – Data Center Expansion Projects:
600 South Federal, Chicago, IL – Data Center Expansion Project – Rubicon provided a design build infrastructure upgrade to support this newly acquired data center space. This project included the installation of a new 600 KW diesel generator, 300 KW UPS and associated HVAC equipment to support the IT design load.
56 Marietta Atlanta, GA – High Rise Development - Rubicon provided design build CM at risk services for this development on the 9th floor of a downtown Atlanta landmark building. The development included 8,500 sq. ft. of raised floor co-location space at 200 watts per foot with infrastructure in place to develop 7th floor at 125 watts per foot over 8,500 sq. ft. Utilize (2) 500 ton cooling towers, plate frame heat exchangers w/ primary-secondary pumping (N+1) expandable by one 500 ton tower and two pumps to allow for 7th floor development. 4MW utility upgrade with new collector bus and 3000A bus to switchgear at 10th floor. Two (2) 1750kW diesel roof mounted generators with fuel rise and redundant pumps. Two (2) 750kVA UPS (N+1 modules on each), (2) 500kVA PDUs w/ RPP distribution. (16) 30 ton CRAC units (N+2).
56 Marietta Atlanta, GA – Low Rise Development - Design-build infrastructure upgrade to emergency power supporting low rise section of facility by installing a 2.5MW diesel generator on the second floor of this downtown historic landmark building. Included associated switchgear, ATS and fully redundant fuel oil supply system. 800kVA UPS supplying power to the 2nd, 3rd & 4th floor to increase watt density to 125 watts per square foot via PDU installation on each floor. Installation of redundant power source to 4th floor PDUs via 8th floor UPS and controlled switching scheme.
Clifton, NJ – CM at Risk of 12,000 sq. ft. of raised floor co-location space at 150 watts per foot utilizing (3) 400 ton fluid coolers, (6) 750KVA UPS modules, 13.4kV main switchgear, (3) 13.4kV substations, (4) 2250kW engine generators, (32) 30 ton CRAC units, and (12) 300 KVA PDU’s. The program was set with an aggressive 12 week schedule for development to be broken out into (2) phases in order to meet customer demand.
Miami, FL - Design and construction of an 800kw engine generator rooftop installation and data center cooling expansion utilizing air cooled computer room air-conditioning systems with roof mounted condensers. Both rooftop installations require structural considerations for a hurricane zone.