Seattle, WA, Fisher Plaza – Rubicon provided design-build construction and commissioning for a UPS and cooling tower expansion project to provide an additional 400kW of UPS capacity and an additional 300 tons of cooling capacity to an existing live data center. Rooftop placement of the cooling tower required additional structural support and coordination with live television broadcast transmission equipment. All work was accomplished with no shut downs or loss or service.

 

Seattle, WA, Sabey Phase I – Rubicon provided design assist construction management for the conversion of commercial real estate to data center use. 9,000 sq. ft. of critical raised floor area, 20,000 sq. ft. total. Tier III infrastructure. 100 watts/sf. density. Compressed construction schedule of 3-1/2 months.

 

Seattle, WA, Sabey Phase II– Rubicon provided design build construction and commissioning for an expansion of existing data space under live load to yield a total of 18,000 sq. ft. of critical raised floor area. Tier III infrastructure. 100 watts/sf density. Compressed construction schedule of 75 days.

 

Seattle, WA, Sabey Phase III – Rubicon provided design and engineering; equipment  procurement and integration; and owner’s representation services for a 7,500 sq. ft. expansion of existing data center space. Included all new M/E/P support equipment for 185watts/sq. ft. density in a Tier III design.

 

Boston, MA, Somerville Data Center Phase I – Rubicon provided design/build CM at risk and commissioning services to provide for additional redundancy and power distribution in existing active data center. Improvements included a new UPS wrap around bypass section, addition of a redundant “B” power path to the critical load, as well as a new UPS distribution section and six (6) 300kVa PDUs for additional branch circuit capacity.

 

Boston, MA, Somerville Data Center Phase IIRubicon provided design/Build CM at risk services for an 8,000 sq. ft. expansion at Internap’s premier Boston location The design leveraged existing utility, generator and UPS systems for 125 watts/ sq. ft. off critical power, while incorporating a new N+1 rooftop chilled water cooling system. The project was completed in 5 months from commencement of design to substantial completion.

 

111 8th Ave – New York, NY – CM at Risk for replacement of 2000 linear feet of 4” sprinkler main covering 70,000 sq ft of active data center raised floor space. All work was performed between the hours of 6PM and 6AM to avoid disruption to normal daily activities. At completion, system under went hydrostatic pressure testing as required by NYC building code. All work completed without any disruption to the data center operations.

 

Atlanta, GA, Data Center Improvements – Rubicon provided general construction services for power and cooling improvements to Internap’s existing data center in downtown Atlanta. Services included installing a 750kVA “catcher” UPS system and (2) 1200A static transfer switches to provide redundancy to the existing A & B UPS systems. Additionally, a new 3000kW engine generator was installed, along with new generator paralleling switchgear. Two existing 1500kW generators were modified and the distribution re-routed to allow for paralleling all (3) generators. All of this work was accomplished without any interruption to the existing clients.

 

Los Angeles, CA New Data Center – Rubicon provided design build construction for 70,000 sf LEED Gold and Green Globes certified flagship data center in Redondo Beach, CA. Innovations included a central equipment mezzanine to increase leasable raised floor space by 15%; free-cooling through the use of custom roof mounted air handling units; packaged outdoor centrifugal chilled water systems; and a concurrently maintainable, Tier III topology.

Usually there is no real reason to visit drugstore every time you need to buy medications. What medicines do patients purchase from the Web? Occasionally humanity need medicines to resolve sexual disfunction. Today varied articles were published about viagra pill. Did read some about “sildenafil 100mg“? If you have any concerns about “Viagra patent expiration“, check with your physician before grab the remedy. Erectile problems can generally indicate serious problems in other area. Also known as erectile dysfunction is defined as the failure to maintain an erection suitable for intercourse. You must be very much cautious while going to order medicines like Viagra.